Environment Canada Environment Canada Canada
Skip navigation (access key: Z)
Website Description (access key: D)
 

Appendix B

Case Studies



Note: The facilities marked with an asterisk were part of a water audit study completed by Proctor and Redfern Limited between December 1991 and April 1992, on behalf of the Interdepartmental Advisory Group on Water Conservation at Federal Facilities. Due to time limitations, the study examined only portions of the water supply system for a two-week period, so projected savings and costs are preliminary in nature. Nevertheless, the study concluded that excellent opportunities exist to achieve significant water reduction at the ten audited sites.

All cost estimates reflect expenditures necessary to procure and install only the recommended devices, and exclude any incidental engineering and construction costs that may in fact be necessary to achieve the stated water reduction at those facilities.

All payback periods are based on these preliminary cost estimates and on current water charges.


Animal Research Centre (AgrC)*

Abstract

1. Background

Under the auspices of the Interdepartmental Advisory Group on Water Conservation at Federal Facilities, member agencies pledged to conduct water audits at selected sites. Agriculture Canada chose the Animal Research Centre as its nominee to demonstrate water conservation/efficiency opportunities with short payback period characteristics.

The Centre is a collection of buildings housing various domestic animals and support materials scattered around the site. Water from a regional main is supplied to 11 animal and maintenance groups. In addition to the predominant water consumption by animals, water is used by laboratories, laundry facilities, cooling, and staff showers, as well as for drain flushing, boiler make-up water and feed preparation process.

The objectives for this study were twofold, to

  • identify and quantify uses of water for each building group and for the entire facility
  • identify and recommend options, based on cost-benefit analysis, for reducing the overall water requirement.

The cost of the study was $27 000.

2. Water audit

To test the integrity of the extensive underground water distribution network, a leak detection survey was undertaken. No leakage was found. Due to the diversity of uses on site, several new water meters were installed. For a 3 week period in January these and the existing meters were read twice a day. The water balance, completed for the main meter and for all individually metered buildings, indicated a 9% loss in the system. The extensive flow monitoring and on-site water use survey indicated that the average estimated water demand for the Centre was 310,000 L/d. During the summer months this demand is expected to increase because of cooling water used in air conditioners.

An estimated 20 000-130 00 L/d of water is used at many barns for 4-5 days in the spring and fall to wash out the manure that has collected over the previous season. In one building over 40% of the total water used by the whole site runs continuously 24 h/d; most of it is used by a drain flushing system, which accounts for an estimated 129 000 L/d. This is a far higher volume than would normally be expected. At the processing plant, an estimated 34 000 L/d is used for walk-in coolers.

3. Water management program

Immediate water reductions can be achieved by replacing the self-flushing urinals with flush valves. The cost of the modifications is $1 500, and with savings of $4 550, a payback period is 4 months. Major water reduction would result from the elimination of once-through cooling at a number of buildings with a payback period of 1.5 years, from the net $23 900 saving and $35 000 modification cost. Pending the outcome of further investigations, there is a potential for savings of up to $35 000/year for the continuously flushing drain lines.

The recommended program includes a range of measures, including routine monitoring of all meters, installations of low-flow devices, replacement of once-through with closed-loop cooling systems, and reduction of flow rate to floor drains. The overall cost of the program, which has 56% volume savings potential, is estimated at $36 600 with a 5-month payback period.


Sir F.G. Banting Building (HWC)*

Abstract

1. Background

Under the auspices of the Interdepartmental Advisory Group on Water Conservation at Federal Facilities, member agencies pledged to conduct water audits at selected sites. Health and Welfare Canada chose the Sir F.G. Banting Building as its nominee to demonstrate water conservation/efficiency opportunities with short payback period characteristics. This institution is a multi-discipline research facility with laboratories and offices in two wings and a large animal wing. Water is supplied from the regional network and, beyond a main meter, the system branches into the three distinct wings of the building. The recirculated hot water system is arranged similarly and serves the animal handling wings for cage washing and hydrobrushing. There is a "shower in" and "shower out" requirement for personnel entering the area. Cold water is used for cooling, the cafeteria, the washrooms, and laboratory use. A distilled water unit fulfills requirements for the research areas of all wings. Since the facility had only one meter and was a high consumer of both cold and hot water, it was decided to submeter both systems for all three wings. The main objectives of this study were to identify and quantify uses of both hot and cold water for each wing and for the entire facility. The study was to identify and recommend options, based on a cost-benefit analysis, for reducing the overall water requirement. The cost of the study was $20 000.

2. Water audit

Over the 3 week monitoring period the average cold and hot water demands of 188 000 L/d and 41 000 L/d, respectively, were measured. The Laboratory wing was the largest user of cold water at 144 000 L/d, of which two-thirds was used for cooling, and an estimated 33 800 L/d consumed by various laboratory uses. A further 39 000 L/d of cold water was used by the air handling units in the Laboratory wing. In the Animal wing total cold water use was estimated at 35 500 L/d, of which the air handling units used 27 500 L/d. The coolant for storage rooms was the major user of cold water (12 600 L/d) in the Communal wing. The greatest volume of hot water (24 000 L/d) was utilized by cage and bottle washers in the Animal wing. A further 9 600 L/d was estimated for use in experiments, cleaning, and washing equipment in the Laboratory wing. Most of the hot water (3 000 L/d) in the Communal wing was used by the kitchen dishwasher.

3. Water management program

Due to the sensitive nature of processes dealing with the animals drinking water supply, cleaning, etc., water reductions in these areas have not been included. Replacing all the fittings in the washrooms and showers with low-flow devices would save $5 000/year in water and energy costs. The $7 650 for the work would give a payback period of 1.5 years. Installation of low-flow valves in washrooms would save $1 430. The installation cost would be $250, and the payback period 0.2 years. Converting water-cooled refrigeration equipment to closed-loop systems would result in yearly savings of $14 000. The modification costs of $30 000 would give a payback period of 2.1 years. A sewer charge rebate could be negotiated with the region to take into account the over $5 600/year in sewer charges currently charged for water that does not discharge to the sewer. Cooling water should be reused for process purposes such as humidification. While hot water use for showers and washrooms would be reduced by the same proportion as cold water, water savings would also contribute to energy cost savings. The overall cost, which has 41% volume savings potential, is estimated at $39 900 with a 10-month payback period.


Chemical Radioactive Ores Building (EMR)*

Abstract

1. Background

Under the auspices of the Interdepartmental Advisory Group On Water Conservation at Federal Facilities, member agencies pledged to conduct water audits at selected sites. Energy, Mines and Resources Canada selected the Chemical Radioactive Ores Building (555 Booth Street) as one of its two nominees to demonstrate water conservation/efficiency opportunities with short payback period characteristics.

The building, constructed in the early 1960s, has three wings accommodating laboratories and administrative offices. All water supplied to the building from a regional water main passes through a meter before being distributed by a riser system in a continuous common loop. All air handling units, drinking water chillers, the domestic hot water system and the hot water perimeter heating system are located in the basement. All special water use equipment (a water distillation unit, a de-ionizer/water purifier, and a cooling tower) are located in the west wing. There are water-cooled AC units throughout the laboratory wings.

Identification of the uses of water at the building and recommendation of options for reducing the overall requirement for water, as well as a cost-benefit analysis for each option were requested of the consultant. The cost of the study was $11 000.

2. Water audit

A 4-week period of flow monitoring indicated that half of the estimated 136 000 L/d average weekday water demand for 555 Booth Street was used by air handling units. Primarily during the winter, these units use approximately 70 000 L/d for air wash and humidification. In the summer months, the air handling demand is replaced by 44 000 L/d needed to cooling water requirements in air conditioner units. Continuously operating flush tank urinals use 15 000 L/d, whereas compressor after-cooling and pump lubrication/cooling account for another 13 000 L/d and 11 000 L/d respectively.

3. Water management program

The installation of low-flow valves on the self-flushing urinal tanks at 555 Booth Street would save $3 450, with a payback of 0.5 years for the $1 750 installation cost. Many water-cooled air conditioning units should be replaced by air-cooled units or converted to a closed-loop cooling system. The latter would cost $20 000 with a 4-year payback period, from the net annual saving of $5 000. A number of cooling loads in the basement, which include drinking fountain chillers, air compressor cooling, and tenant equipment, should be converted to a closed-loop cooling system. The savings of $12 000 and modification cost of $10 000 will give a 10-month payback period. A sewer charge rebate could also be negotiated with the municipality to take into account over $6 000 in sewer charges currently charged for water that does not discharge to the sewer. When water must be used for cooling, it should be reutilised for process purposes such as humidification. The overall cost of the program, which has 42% volume savings potential, is estimated at $32 250 with a 12-month payback period.


Canada Centre for Inland Waters (EC)

Abstract

1. Background

The CCIW research/laboratory establishment, built around 1967 in Hamilton, occupies 47 700 m2 of mixed use floor area in seven wings of a single structure. The facility has, in the past, taken a number of water conserving and cost saving actions. Since 1985, uncontaminated water has been diverted through a storm sewer outlet to Hamilton harbour. This resulted in decreased flows to the Hamilton Wastewater Treatment Plant, and as a consequence, credit continues to be received on sewer surcharges from the local water authority. Further actions included

  • replacement of manual flush units with automatic ones in urinals
  • installation of water meters to monitor water use and to allocate costs
  • use of harbour water for lawn watering
  • reduction in flush/refill frequency in tanks and flumes by cutting back the algae growth rate

All these actions have resulted in an annual water and sewerage bill of about $160 000 after rebates. To further enhance water conservation at the facility, a consultant was retained to complete a water efficiency audit. The cost of the study was $35 000.

2. Water audit

A 3-week period of flow monitoring and an on-site water use survey indicated that the average estimated water demand for the institution was 23 800 m3/month. Over the recording period, the base load of water use was about 70% continuous flow. Water use tended to concentrate in two main areas:

  • fisheries laboratory (183 m3/d average, of which 174 m3/d is discharged)
  • administration and laboratory wing (299 m3/d average, of which 200 m3/d is used for once-through cooling and subsequently discharged)

Water use was split into four categories represented by a percentage of the city water intake: cooling (50%), process (36%), domestic (7%), and laboratory (7%). Water intake totalled 717 m3/d including 7% unaccounted-for water flow. The estimated per capita domestic use in the facility is 65 L/d.

3. Water management program

The main recommendation concerns the curtailment of cooling water demands. Due to CCIW's fortunate location, all cooling water may be drawn directly from the harbour. The cost of intake development to replace ca 327 m3/d of city water was estimated at $101,000. The estimated savings at current water costs are $53 000/year for a payback period of under 2 years.

At 36%, the fisheries laboratories' tanks use the second largest volume of city water. The cost of reusing some of the once-through cooling water for process applications ($23 350) would result in annual savings of $22 600, for a 1.03-year payback.

With water-saving devices already in place, only user habit changes could produce small savings. It was also proposed to

  • move certain operations at the laboratories to periods when lower volumes of water are used
  • reactivate the existing pressure-reduced cold water network to achieve water use reductions
  • more thoroughly use existing/new water meters to monitor use and ensure that reductions maintained in the future

Curve Lake First Nation School (INAC)*

Abstract

1. Background

Under the auspices of the Interdepartmental Advisory Group on Water Conservation at Federal Facilities, member agencies pledged to conduct water audits at selected sites. Indian and Northern Affairs selected the Curve Lake First Nation School as one of its two nominees to demonstrate water conservation/efficiency opportunities with short payback period characteristics.

It is primarily an elementary school but offers some adult education programs, operating 194 days per year with a current enrollment of 53 students and 8 staff members. Adult education classes, with 7 students and one instructor, are conducted 335 days/year in a portable classroom located on the elementary school site. Generally, both elementary and adult students occupy the school weekdays between 0845 and 1600 hours. The domestic cold water supply at the elementary school and the portable classroom is pumped from a well (no permanent flow meter) located on the school site.

The objective for this study was the identification of present water uses at the school site. A cost-benefit analysis of the recommended measures for reducing the overall requirement for water was also included. The cost of the study was $6 000.

2. Water audit

As stated previously, there was no existing water meter at the facility and a pump supplied water to the school on demand. To document water consumption by the facility, a clip-on meter was used to record pump operation.

A week of flow monitoring indicated that the average estimated water demand for the institution was 3 500 L/d, which was reasonable for a small facility. The domestic portion of the water, 2 500 L/d, is used in the washrooms. This includes a system loss of 270 L/d, attributed to a leaking toilet in the boys' washroom. Process water, 1 060 L/d in total, was estimated for general use (including cleaning) in the classrooms and daily flushing of the pipes at the drinking fountain.

Commencing with the summer of 1992, a lawn watering program will be implemented; however, its effects were not considered in the audit.

3. Water management program

The only water reduction alternative is in the domestic uses. Retrofitting the plumbing fixtures with low-flow devices would give an annual saving of $850. The observed leak in the boys' washroom could cost as much as $400/year. At an estimated cost of under $50 to fix it, this would pay back in about one month.

The overall cost of the program, which has 39% volume savings potential, is estimated at $3 300 with a 32-month payback period.


Douglas Border Crossing (RC-CE)*

Abstract

1. Background

Under the auspices of the Interdepartmental Advisory Group on Water Conservation at Federal Facilities, member agencies pledged to conduct water audits at selected sites. Revenue Canada, Customs and Excise, selected the Douglas, B.C., border crossing station as one of its two nominees to demonstrate water conservation/efficiency opportunities with short payback period characteristics. It is a smaller than average facility with the Customs and Immigration departments contained in a common block processing primarily noncommercial border traffic. In 1990, there were about 5.3 million cross-border travellers processed by this facility. At one time, domestic cold water was supplied to the facility from the United States, but in the past few years the water main was replaced, and water is now purchased from Canadian sources. Two existing meters are located in hand holes at the municipally operated water main, making the water supply to the Immigration and Customs areas entirely separate. The water supply is generally limited to drinking fountains, washrooms, and make-up water for the domestic hot water heater and the hot water heating system.

The water audit study was to identify and quantify uses of water for the entire facility as well as to identify and recommend options for reducing the overall requirement for water and to carry out a cost-benefit analysis for each option. The cost of the study was $10 000.

2. Water audit

Flowmeter reading for the Immigration building was intended to continue for a 3-week period, but seasonal rains flooded the meter chamber so that the meter could not be read. No flooding problems arose in the meter chamber for the Customs building, and the meter was monitored over a 5-week period. Separate individual balances for the Immigration and Customs building totalled 18 100 L/d and 3 800 L/d respectively. Most of the water, 17 900 L/d, in the Immigration building is consumed for domestic purposes in the public washrooms and drinking fountains. Process water is used in the kitchen at an estimated 190 L/d and the lawns are watered in the summer. The domestic water use at the Customs building is estimated to be 3 020 L/d. During the busier summer months the above figures will increase significantly. The process water uses are in the kitchen and at the alcohol disposal tank with 780 L/d. An exterior sprinkler system waters the lawns in the summer.

3. Water management program

If all the lavatories were fitted with aerators and/or flow restrictors, and all the water closets and urinals were fitted with low-flow flush valves, the total domestic water consumption would be reduced by an estimated 4 700 L/d. This would amount to savings of $450/year. The cost of the proposed renovations would be approximately $3 150 for an estimated payback period of 7 year. Since summer time will bring more people and more domestic water use, a significantly shorter payback period can be expected. Reducing the present flush rate by throttling back the valve to the flush tank in the men's public washroom would produce an immediate savings of approximately 7 000 L/d. Water and cost savings would amount to 2 555 000 L/yr or $670.

The overall cost of the program, which has 39% volume savings potential, is estimated at $3 150 with an 34-month payback period.


Fuel Research Laboratory Building (EMR)*

Abstract

1. Background

Under the auspices of the Interdepartmental Advisory Group on Water Conservation at Federal Facilities, member agencies pledged to conduct water audits at selected sites. Energy, Mines and Resources Canada chose the Fuel Research Laboratory Building (562 Booth Street) as one of its two nominees to demonstrate water conservation/efficiency opportunities with short payback period characteristics.

The Laboratory, constructed about 1930, is a three-storey building and was selected for water audit because its historical water use was high for its building size. The building has a floor area of 2 758 m2 and a staff of 18. The domestic cold water is supplied to the facility by city water mains operated by the Regional Municipality of Ottawa-Carleton. Beyond the water meter, the domestic cold water branches into three lines to serve the south, north, and centre of the building. At one time, the south branch was used to supply air conditioning units and laboratory sinks; however, most of the air conditioning units and sinks have been disconnected. The centre branch supplies make-up water to the domestic hot water system. The north branch supplies the remainder of the building, including washrooms, laboratories, one large walk-in refrigeration unit, and one small unit. Identification of the uses of water at the building and recommendation of options for reducing the overall requirement for water, as well as a cost-benefit analysis for each option, were requested of the consultant. The cost of the study was $7 000.

2. Water audit

Meter readings for the two 2-week periods produced an average estimated water demand of 8 500 L/d. As a note of interest, a video camera was used to take hourly readings for two days due to the lack of personnel available.The completed water balance indicated that domestic water was used by the 18 staff in the washrooms at an estimated 600 L/d. The largest flow, 3 000 L/d, is at two flush tanks in the men's washrooms. The once-through cooling for the building has been reduced in recent years. Two large walk-in refrigerator/freezers have been removed, and the use of room air conditioning units in the summer months has been significantly reduced. The remaining walk-in refrigerator/freezers use an estimated total of 3 000 L/d. An estimated 1 900 L/d is used in the laboratories and support rooms in the building. The historical water records for 562 Booth Street indicated a ten times greater flow into the building than was recorded during the audit. The facility staff have been alerted to this discrepancy and will investigate the matter.

3. Water management program

The installation of new flush valves on 2 self-flushing urinals in the washrooms will save $1 300/year, with a 0.3-year payback period, for a modification cost of $375. A closed-loop cooling system could be installed for the water-cooled refrigeration systems for a savings of $900/year. The modifications cost would be $5 000 and the resulting payback period 5-6 years. The water-cooled air conditioning units should continue to be removed or replaced with air-cooled units. The ten times discrepancy in flowmeter reading has the potential for a reduction in the water bill of $33 600/year.

The overall cost of the program, which has 97% volume savings potential, is estimated at $5 375 with a 2-month payback period.


Lacolle Border Crossing (RC-CE)*

Abstract

1. Background

Under the auspices of the Interdepartmental Advisory Group on Water Conservation at Federal Facilities, member agencies pledged to conduct water audits at selected sites. Revenue Canada, Customs and Excise, selected the Lacolle, P.Q., border crossing station as one of its two nominees to demonstrate water conservation/efficiency opportunities with short payback period characteristics. The crossing, regulating both commercial and noncommercial cross border traffic, comprises several buildings for Immigration and Customs operations. It processed approximately 2.7 million travellers in 1990. Domestic cold water for the site is supplied by a well and reservoir system. Some treatment of the water is undertaken at the reservoir before its discharge to the site distribution system. The main meter is located immediately after the domestic cold water pumps, and a sub-meter is in the Duty Free Shop. All water used on the site passes through the main meter except during periods of high flow, at summer weekend evening hours. On these occasions when the domestic cold water system pressure drops, the fire pumps operate to increase the water supply. Most water is used in the washrooms and some air conditioning units; a small amount of make-up water is needed for the hot water heating system. Water use by the sewage treatment plant is minimal and infrequent. The water audit was to identify and quantify uses of water as well as to identify and recommend options for reducing the facility's overall water requirements and to carry out a cost-benefit analysis. The cost of the study was $11 000.

2. Water audit

A 2-week period of flow monitoring indicated that the average estimated water demand for the facility is 22 900 L/d. Because of the nature of operations, the busier summer months will increase this demand significantly. As the station has an extensive underground network, about 3 000 m, there is potential for leakage. Routine detection survey indicated no leaks. The main areas of water use at the station are in the public washrooms, with an estimated 8 400 L/d used. The staff washrooms, lunchrooms, and locker rooms use an estimated 4 100 L/d; the Duty Free Shop uses 3 700 L/d of water in the washrooms; and an air conditioning unit uses an estimated 10 000 L/d. Summer cooling water demand will increase with the use of two additional air conditioners.

3. Water management program

If all the lavatories were fitted with flow restrictors and all washroom fixtures were fitted with low-flow flush valves, the total domestic water consumption would be reduced by an estimated 3,600 L/d. For the estimated $8,650 retrofit cost, a 1.6-yr payback period would result. A closed-loop cooling system for the air conditioning units could be installed for approximately $10,000. This system would save 7 300 000 L/yr. The estimated annual cost savings would be the water saved, less the cost of electrical energy required to run the pump and fans on the closed-loop cooler. The estimated water savings are $30 150/year; when the operating cost of $1 300 is taken into account, the net savings are $28 850. The resulting payback period is 0.4 years. An additional benefit would be the elimination of seasonal demands, thereby reducing the need for the fire pump to operate in summer months to maintain system pressure. The overall cost of the program, which has 69% volume savings potential, is estimated at $18 650 with a 7-month payback period.


Major-General G.R. Pearkes Building (PWC)*

Abstract

1. Background

Under the auspices of the Interdepartmental Advisory Group on Water Conservation at Federal Facilities, member agencies pledged to conduct water audits at selected sites. Public Works Canada chose the Major-General George R. Pearkes Building (101 Colonel By Drive) as its nominee to demonstrate water conservation/efficiency opportunities with short payback period characteristics. The complex is essentially an office building comprised of two 20-storey towers and a central building of 12 storeys. The domestic cold water supply system for the entire complex is controlled from the North Tower, where city water enters at the basement level mechanical room. The system consists of three components: the city pressure system, a low rise pressure system, and a high rise pressure system serving various heights of the complex. Domestic water is used in the washroom facilities, for air conditioning units, and kitchen refrigerators and freezers, as well as in cooling tower make-up during the summer months. This water audit study was to identify and quantify uses of water for the entire facility as well as to identify and recommend options for reducing the overall requirement for water and to carry out a cost-benefit analysis for each option. The cost of the study was $10 000.

2. Water audit

The existing water meter was read twice daily for a 3-week period and exhibited typical water use patterns for an office complex with an estimated average of 429 000 L/d. Most of the 20 floors have two women's and two men's washrooms, which use an estimated 117 500 L/d of water. In addition, continuously operating self-flushing urinals in many of the washrooms account for an estimated 116 000 L/d. Cooling is accomplished by once-through city water, a closed-loop cooling tower between the 11th and 20th floors, and chilled water from the central plant. The city water air conditioning units located throughout the building account for an estimated 129 800 L/d. A further estimated 17 300 L/d is used as cooling tower make-up in the summer. Kitchen fridges and freezers and serving hatches use an estimated 25 000 L/d of cooling water. The kitchen dishwasher and pre-scrubbing machine is the largest process water user at an estimated 13 000 L/d. In the summer, the outside lawns are watered by an estimated 70 000 L/d a day.

3. Water management program

The installation of low-flow valves on up to 40 self-flushing urinal tanks will save $40 000/year. For a modification cost of $10 000, the payback period will be 3 months. The large number of water-cooled air conditioning units should be converted to chilled water or a closed-loop cooling system. A net savings of $20 000 would result in a payback period of 2 year when the modification cost of $40 000 is taken into account. Other water-cooled equipment, including drinking fountain chillers and the cafeteria fridges and freezers, should be converted to a chilled water or closed-loop cooling system at a cost of $10 000. The savings of $4 500/year will give a payback period of 2.2 years. At the soil table in the cafeteria, control of water use could save up to $1 580/year. When cooling water is unavoidable, it should be reused for process purposes such as plant watering or floor drain priming. It was noted during the audit that generally the larger pump operates continuously and the small pump infrequently. There was no installed standby large pump, so consideration should be given to improve the current standby provision. The overall cost of the program, which has 54% volume savings potential, is estimated at $60 000 with an 11-month payback period.


Ottawa International Airport (TC)

Abstract

1. Background

Under the sponsorship of the Interdepartmental Advisory Group on Water Conservation at Federal Facilities, Transport Canada has selected the Ottawa International Airport (OIA) as its test site to demonstrate water conservation/efficiency opportunities. The OIA shares the airport complex with NRC and DND areas of operations. The audit was restricted to only those Transport Canada facilities where most of the water consumption was assumed to occur, including the terminal and support/maintenance buildings, hangars, and control tower. The airport complex receives potable water from regional municipality sources via storage and treatment on DND territory. It is pumped to all users with OIA being served by two unmetered water mains.

The audit objectives included

  • undertaking a system balance to account for water used throughout the facility
  • identifying and quantifying characteristic water uses for each selected building
  • identifying and recommending options, based on cost-benefit analysis, for improving water efficiency and reducing the overall water requirement

The cost of the study was $30 000.

2. Water audit

Temporary insertion meters and clamp-on meters, attached on supply lines, and all existing meters were monitored for up to 2 week. The average estimated water demand was found to be 672 m3/d, indicating that the audited buildings accounted for almost 62% of the total demand. Over the recording period, the base nighttime flow was 192 m3/d. Almost 50% of all OIA consumption was concentrated in the main terminal building (218 m3/d) where both the restaurant and flight kitchen are located. Washrooms for the travelling public and staff used 70 m3/d. Consumption demands, due to air conditioning and lawn watering, will likely increase during the summer. Several washrooms and a canteen contribute to the 27 m3/d used in the flight services hangar representing approximately 10% of all OIA uses.

Leak detection survey indicated a tight system; therefore, buildings not monitored account for the balance of water use. Further investigations are necessary to determine whether any of these buildings consume significant volumes of water.

3. Water management program

The main recommendation concerns the replacement of most existing flow meters, which are oversized and underrate the flow, particularly those used for billing purposes. A number of discrepancies between the maintenance computer and the site meters were observed. Relays should be checked to ensure that all communications with the computer are accurate. In addition, permanent meters should be installed on both supply lines to confirm billing from DND and to monitor consumption trends for possible losses.

Throughout the audit some wastage were identified in the walk-in coolers. Savings may be realized by changing to a closed-loop system but payback periods would be high. The practice of supplanting automatic shut off valves on washroom fixtures should continue. Low-flow nozzles should be installed in the maintenance hangar to reduce equipment cleaning water use. A method of billing customers for the water used in the Aircraft Sewerage Disposal Building should be investigated.

Supplying lawn irrigation needs from local reactivated backup wells and implementation of an annual leakage detection survey should be investigated.


Parliament Hill, Centre Block (HofC)*

Abstract

1. Background

Under the auspices of the Interdepartmental Advisory Group on Water Conservation at Federal Facilities, member agencies pledged to conduct water audits at selected sites. House of Commons officials selected the Centre Block to demonstrate water conservation/efficiency opportunities with short payback period characteristics. Most of the internal piping and appurtenances in the Centre Block date to the reconstruction of the early 1920s. The external domestic cold water supply is unique in that it actually forms part of the internal system with entry to Centre Block from the East and West Blocks. It is therefore possible for water to flow out of Centre Block at either end of the building. There are no water meters located on the internal watermain system in the building, and past water usage rates have been assessed from meters recording water consumption for all of Parliament Hill. City water pressure being insufficient, most of the building is supplied from a pumped storage system. Water is pumped to storage reservoirs located in the sixth floor towers. Domestic cold and hot water supply systems are duplicated for the Commons and the Senate sides. Special water use areas are the cafeteria and restaurant. During the summer, offices located on the south side of Centre Block are supplied with air conditioning units which operate with once-through cooling water. The water audit was to identify the uses of water for the entire facility as well as to recommend options for reducing the overall requirement for water and to carry out a cost-benefit analysis for each option. The cost of the study was $23 400.

2. Water audit

Due to the lack of installed flow meters and the unacceptability of both insertion meters and clamp-on devices, the times of operation of the domestic cold water pumps in Centre Block were measured indirectly, and flow was calculated as 204 000 L/d for a 3-week period. For future monitoring purposes, the most accurate water consumption data will be generated by the installation of permanent flowmeters. Public washrooms used an estimated 63,000 L/d, and private washrooms for MPs' offices an estimated 6 000 L/d. In the summer an estimated 160 000 L/d is used by water-cooled room air conditioning units and 45 000 L/d for other cooling purposes. A compressor after-cooler accounted for an estimated 13 000 L/d. The main volume in the process category was an unusually high estimated 33 000 L/d for heating system make-up. Two dishwashers at the restaurant and cafeteria use a further 12 000 L/d. In the summer the lawns are watered by an estimated 87,000 L/d, and a continuous flow of 33 000 L/d is estimated to be used at the Centennial Flame Fountain.

3. Water management program

All washrooms should be fitted with low-flow, or flow restrictive devices. The cost of the modifications is $18 750, and the savings of $6 275/year will give a payback period of 3.0 years. Installation of low-flow valves on 8 self-flushing urinal tanks will save $6 000 for a 4-month payback period on the modification cost of $2 000. The water-cooled refrigeration equipment should be converted to closed-loop systems. The modifications would result in a net saving of $24 700/year, and with the cost of the works being $30 000, the resulting payback period would be 1.2 years. Fixing an assumed leak in the hot water heating system would save over $8 000/year in water losses. The overall cost of the program, which has 34% volume savings potential, is estimated at $51 250 with a 12-month payback period.


Walpole Island First Nation School (INAC)*

Abstract

1. Background

Under the auspices of the Interdepartmental Advisory Group on Water Conservation at Federal Facilities, member agencies pledged to conduct water audits at selected sites. Indian and Northern Affairs selected the Walpole Island First Nation School as one of its two nominees to demonstrate water conservation/efficiency opportunities with short payback period characteristics.

Walpole Island First Nation School, located on the Walpole Island Reserve in southern Ontario, is an elementary school, from kindergarten to grade 8, with some special amenities. It operates a normal school year with 365 students and 30 teachers. Generally, the school is occupied between 0830 and 1530 hours on weekdays. Occasionally, extracurricular functions take place, including after-school sports events and weekend craft shows. An existing flowmeter records the domestic cold water supplied from the Reserve's water distribution system.

The objective for this study was the identification of present water uses at the school site. A cost-benefit analysis of the recommended measures for reducing the overall requirement for water was also included. The cost of the study was $6 000.

2. Water audit

Most of the fixtures within the school (lavatories, water closets, and laboratory sinks) represent no extraordinary water uses. Drinking fountains within the facility have been turned off as a result of misuse by the students. The student cafeteria serves breakfasts to students during the winter season. The average daily flow for the entire 7-week flowmeter monitoring period was 12,100 L/d. The main area of water use is for domestic purposes in the washrooms at 10,100 L/d. Visible leaks at six locations throughout the school account for a total of 1 460 L/d of water. The process water used in the laundry room is estimated at 230 L/d. The kitchen dishwasher operates seasonally and accounts for an estimated 100 L/d of water. Janitor's sinks and the laboratories use a further 100 L/d each. A small amount of lawn watering is performed in the summer.

3. Water management program

If all the lavatories were fitted with aerators and/or flow restrictors, and all the water closets and urinals (excluding the self-flushing ones) fitted with low-flow flush valves, the total domestic water consumption would be reduced by 3 480 L/d. The cost of the proposed renovations would be approximately $11 300 for an estimated payback period of over 28 years, an unacceptably long period. The major area for reduction of domestic water lies in the self-flushing urinals. The installation of low-flow valves on the self-flushing urinal tanks would save an estimated $300/year. A 1.7-year payback would result from the $500 installation cost. The need for proper maintenance is also very important. As observed during our site visit, several leaks were detected and, unchecked, these leaks could cost as much as $300/year. The estimated cost of $100 to repair these leaks would give a payback period of 0.33 years.

The overall cost of the program, which has 35% volume savings potential, is estimated at $600 with a 12-month payback period.


Warkworth Institution (CSC)

Abstract

1. Background

The Warkworth Institution is a medium security federally owned correctional facility, located in Brighton Township, Ontario.The penitentiary accomodates up to 590 inmates and 308 daytime staff in over; 40 buildings on the site. Water is supplied to the institution from its own filtration plant which draws water from the Trent River. The collected sanitary sewage receives secondary treatment in wastewater treatment plant on site.

The Institution currently undertakes a rejuvenation program of the water supply and treatment and of sewage treatment facilities. Several objectives were established for this study at the Institution: to identify and quantify sources and uses of water (peak flow, time series of flows, losses, etc.) for each building and for the entire facility as well as amounts and types of wastewater; to identify and recommend options for reducing the overall requirement for water {water saving devices, user habit changes, etc.) and analyze their impacts; to carry out a cost-benefit analysis for each option. The: cost of fhe study was $56 000.

2. Water audit

A 4-week period of flow monitoring and an on-site water use survey indicated that the average estimated water demand for the institution was 259 000 L/d. During the summer months this demand increases to 519 000 L/d, primarily attributed to cooling water used in air conditioners. When the institution's facilities expand and if all uses remain unchanged, the projected demand will increase by 9%. A 262 000 L/d difference is detected between measured water supply rate and estimated demand, indicating losses in the system. Results from sewage flow monitoring at the treatment plant do not exhibit these losses resurfacing as infiltration. The calculated per capita water demand of 668 L/d is comparable to similar facilities; however, it is markedly higher than values quoted in literature.

It was recommended to verify wastewater treatment plant flows by additional flow monitoring.

3. Water management program

Reduction in water use and peak demand at the Institution is attainable by altering components at various points in the supply system (toilets, showers, air conditioners, etc.). Evaluation of cost effectiveness of water reduction measures for toilets and handsinks indicates insignificant gains, whereas the same for all other uses turn out to be acceptable. Implementation of the recommended program would result in 115 ML/yr water savings with a corresponding 40% drop in peak demand. Total cost of the program is estimated at $38 000 with a 2-year payback period. The cost excludes distribution system repair.

The recommended program includes measures from routine monitoring of new meters and eliminating system leaks through installation of low-flow showerheads and tap aerators, replacement of water with air cooled AC units with or without auto timers, and reduction of flow rate to compressors, to installation of auto shut-off outdoor spraying devices.

To maintain the success of the program, staff education, daily flow monitoring, routine inspection and repair of the supply system, installation of water efficient devices, and periodical assessment and update of this program is recommended.


---
The Green LaneTM, Environment Canada's World Wide Web site